First Rashid rover launched
AchievedThe first Rashid rover, about 10 kg, launched on ispace's HAKUTO-R Mission 1 lander.
Why it matters: The UAE's first attempt to put a rover on the Moon.
Science mission
✓ Concept✓ Design✓ BuildTest · NowCertificationIn service
Rashid Rover 2 (Emirates Lunar Mission)
Second Emirati rover after Rashid 1 was lost; builds UAE capability in lunar mobility, payload integration and international science partnerships.
Rashid Rover 2 is the UAE's second lunar rover, built and run by the Mohammed Bin Rashid Space Centre (MBRSC) in Dubai under the Emirates Lunar Mission, which is funded by the ICT Fund of the Telecommunications and Digital Government Regulatory Authority (TDRA). It aims to make the UAE the second country to land on the far side of the Moon.
The first Rashid rover (about 10 kg, the lightest lunar rover built) launched in December 2022 on ispace's HAKUTO-R Mission 1 lander, and was lost in April 2023 when the lander crashed. Sheikh Mohammed bin Rashid announced Rashid Rover 2 in April 2023. In February 2024 MBRSC said it would change the landing site. On 22 May 2025 MBRSC signed with Firefly Aerospace to fly the rover on Blue Ghost Mission 2.
Science aims: the rover carries several cameras and probes to study the plasma environment, geology and thermal conditions, soil properties, surface temperatures and the photoelectron sheath (a thin layer of charged particles above the sunlit surface). It tests how different wheel materials stand up to lunar dust, to inform future spacesuits and habitats. It also carries RTx, a ground-penetrating radar transmitter whose signals, picked up by NASA's LuSEE-Night instrument on the lander, can probe up to about 100 m below the surface. The mission is planned to last about ten days. Mass and dimensions have not been published.
Key dates: CNES delivered two CASPEX cameras and a camera module in November 2024; MBRSC and CNES signed a memorandum of understanding on 15 September 2025; thermal vacuum tests at CNES, Toulouse, and vibration tests at EARTH in the UAE in 2025; development declared complete and rover shipped to the USA in November 2025; interface, wireless and drive-off tests with the Blue Ghost lander reported on 11 December 2025; RTx integration completed 29 September 2026; Mission Control Space Services selected for the rover's wireless communications, 7 October 2026.
Setbacks: launch was planned for 2026 (early 2026 in some reports, second half of 2026 in CNES's). Firefly now lists Blue Ghost Mission 2 as no earlier than 2027; no reason has been published.
Status (2026): the rover is in payload integration and mission-readiness activities with Firefly. Blue Ghost Mission 2 will launch on a SpaceX Falcon 9 with Firefly's Elytra Dark orbital vehicle, which will release ESA's Lunar Pathfinder satellite in lunar orbit and then the Blue Ghost lander, which lands on the far side near Nassau Crater about 44 days after launch.
Next: launch no earlier than 2027, then at least ten days of surface operations.
Showing 1–4 of 7
December 2022
The first Rashid rover, about 10 kg, launched on ispace's HAKUTO-R Mission 1 lander.
Why it matters: The UAE's first attempt to put a rover on the Moon.
April 2023
The HAKUTO-R lander crashed, losing the first rover; Sheikh Mohammed bin Rashid announced Rashid Rover 2.
Why it matters: Showed the UAE's commitment to lunar work despite the loss.
November 2024
CNES delivered two CASPEX cameras and a camera module for the rover.
Why it matters: Continues a working UAE–France space partnership.
22 May 2025
MBRSC signed with Firefly Aerospace to fly the rover on Blue Ghost Mission 2 to the far side of the Moon.
Why it matters: Gives the rover a ride with a lander maker that has already landed on the Moon.
15 September 2025
MBRSC and CNES signed a memorandum of understanding covering cameras, image processing and mission support from Toulouse.
Why it matters: Formalises European technical support for the mission.
November 2025
MBRSC declared development complete and shipped the rover to the USA for integration with the lander.
Why it matters: Moves the mission from build to integration.
11 December 2025
Interface, wireless and drive-off tests with the Blue Ghost lander were reported complete.
Why it matters: Checks that the rover can talk to the lander and roll off it safely.
2025
The rover passed thermal vacuum tests at CNES, Toulouse, and vibration tests simulating launch and landing at the EARTH test facility in the UAE.
Why it matters: In-country environmental testing builds UAE space test capability for other programmes.
29 September 2026
Integration of RTx, a ground-penetrating radar transmitter whose signals NASA's LuSEE-Night instrument will receive, was completed; it can probe up to about 100 m below the surface.
Why it matters: Adds US partners (NASA, Brookhaven, Heliospace, SwRI) and deeper science value.
7 October 2026
Mission Control Space Services of Ottawa was selected for the rover's wireless communications, with Canadian Space Agency support.
Why it matters: Shows a small mission drawing suppliers from several countries.
No earlier than 2027 (earlier planned for 2026)
Blue Ghost Mission 2 is to launch on a SpaceX Falcon 9 with Firefly's Elytra Dark orbital vehicle, which also releases ESA's Lunar Pathfinder satellite. Firefly lists the mission as no earlier than 2027; no reason for the slip has been given.
What to watch: a firm launch date from Firefly.
About 44 days after launch
The lander is to touch down on the far side near Nassau Crater, then the rover operates for about ten days.
What to watch: landing success; the UAE would be the second country to land on the far side.
Showing 1–1 of 3
Partners as published by MBRSC, Firefly, CNES and partner companies to Oct 2026. Rover mass, dimensions and the full instrument list have not been published. Launch has moved from 2026 to no earlier than 2027.
Showing 1–1 of 3
| Compared item | Rashid Rover 2 (reference) | Rashid Rover 1 (UAE) | Yutu-2 (China) | Pragyan (India) |
|---|---|---|---|---|
| Mass | Not published | About 10 kg | 140 kg | About 26 kg |
| Landing site | Lunar far side, near Nassau Crater (Firefly) | Atlas crater (planned, near side) | Von Kármán crater, far side | Near lunar south pole |
| Launch / landing | Launch no earlier than 2027 on Falcon 9 / Blue Ghost | HAKUTO-R Mission 1, launched Dec 2022 | Launched 7 Dec 2018 (Long March 3B); landed 3 Jan 2019 | Launched 14 Jul 2023 (LVM3-M4); landed 23 Aug 2023 |
| Planned surface life | About 10 days | Not verified | Three months nominal | About one lunar day (14 Earth days) |
| Outcome | Not yet flown | Lost in lander crash, April 2023 | Still active as of Sept 2025 | Drove 101.4 m; mission ended after 12 days |
| Operator | MBRSC (UAE) | MBRSC | CNSA | ISRO |