Air mobility

Eve eVTOL (Eve 100) – engineering prototype and conforming prototypes

✓ Concept✓ Design✓ BuildTest · NowCertificationIn service

Eve eVTOL (Eve 100) – engineering prototype and conforming prototypes

Illustration
Country and region
Brazil · Latin America and the Caribbean
Lead organisations
Eve Air Mobility (Embraer group); ANAC (Brazilian civil aviation authority)
Last milestone
Q3 2026 update: 73 flights, partial transition to 45 kt, 8–10 flights from full transition; FlyBIS binding order (2 firm + 10 rights) (5 Nov 2026)
Next milestone
Full transition to wing-borne flight; first conforming prototype assembly; ANAC type certification (Full transition before end 2026; conforming prototype assembly early 2027; next piloted flight H2 2027; ANAC certification and FAA validation targeted end 2028)

Why it matters

Gives Latin America its own certified eVTOL maker and supply chain, using Embraer's engineering and support network to serve regional urban air mobility.

Eve is developing a piloted electric air taxi for four passengers. It uses a "lift and cruise" layout: eight fixed rotors lift the aircraft for take-off and landing, and a rear pusher propeller, driven by two motors for redundancy, pushes it forward so the wing carries it in cruise. The design range is about 100 km (60 miles). Eve is based in São José dos Campos, São Paulo, and Embraer is its controlling shareholder. Embraer supplies about 1,000 engineers, prototype assembly, industrialisation, quality, logistics and support under a services agreement.

Origins: Embraer showed an early concept on 8 May 2018. Eve was launched as a company on 15 October 2020, the first spin-off from Embraer's EmbraerX innovation unit. Embraer asked ANAC to certify the aircraft on 10 February 2022. Eve listed on the New York Stock Exchange (EVEX) in May 2022 after merging with Zanite Acquisition Corp, and has also been listed on Brazil's B3 exchange since December 2025.

Key dates: in mid-2023 Embraer chose Taubaté, São Paulo, for the first production site. Eve named most of its main suppliers between June 2023 and July 2024, and the first full-size prototype was shown at the Farnborough Airshow in July 2024. On 16 June 2025 São Paulo helicopter operator Revo signed the first binding agreement, for up to 50 aircraft. The uncrewed engineering prototype first hovered at Embraer's Gavião Peixoto test site on 19 December 2025, and the hover phase ended in April 2026. In December 2025 Eve picked BETA Technologies to supply the pusher motors for conforming and production aircraft. The first partial transition flight was announced in early August 2026: 3 minutes 9 seconds, 90 ft, a steady 27 knots, with the pusher propeller running.

Setbacks: Eve once aimed for certification and service in 2026. The target moved to 2027, and then, in mid-2026, to 2028. Eve said the extra time allows 12 months of certification flight testing. The binding FlyBIS deal (November 2026) covers up to 12 aircraft, much smaller than the 40 in its 2022 letter of intent. The total backlog fell from about 2,700 aircraft (August 2026) to about 2,500 (November 2026).

Showing 1–4 of 6

Milestone path

  1. 15 Oct 2020

    Eve spun off from EmbraerX

    Achieved

    Embraer launched Eve as the first spin-off from its EmbraerX innovation unit, building on an eVTOL concept first shown in May 2018.

    Why it matters: It put Embraer's airframe, certification and support know-how behind an air taxi start-up from day one.

  2. 10 Feb 2022

    Certification application to ANAC

    Achieved

    Embraer asked Brazil's civil aviation authority, ANAC, to certify the Eve aircraft.

    Why it matters: ANAC is the lead authority; FAA and EASA approvals follow from its work.

  3. 18 Jun 2023

    First main suppliers named

    Achieved

    At the Paris Air Show Eve named Nidec Aerospace (electric propulsion), BAE Systems (energy storage) and DUC Hélices (rotors and propeller); about a dozen more followed by July 2024.

    Why it matters: Supplier choices lock in much of the aircraft's cost and certification work.

  4. Mid-2023 (June per Wikipedia; reported 25 Jul 2023)

    Taubaté chosen for production

    Latest

    Eve and Embraer named Taubaté, São Paulo, as the first eVTOL production site, on Embraer land.

    Why it matters: A Brazilian production base links the programme to Embraer's existing supply chain in São Paulo state.

Showing 1–1 of 4

Systems and suppliers

Aircraft developer and industrial partner

Eve Air Mobility (Brazil)
Designs the aircraft and runs the programme; also offers TechCare support and Vector air traffic software.
Embraer (Brazil)
Controlling shareholder; engineering, prototype assembly at Gavião Peixoto, industrialisation, quality, logistics and support under a services agreement; production site at Taubaté.

Propulsion and energy

Nidec Aerospace (USA; joint venture of Nidec Corporation, Japan, and Embraer)· not listed in the Directory
Electric propulsion system; lift motors (final lift motor running at Nidec in Japan, Nov 2026).
Nidec Aerospace (Nidec–Embraer joint venture)· not listed in the Directory
electric propulsion system
BAE Systems· not listed in the Directory
energy storage system (batteries)
Intergalactic· not listed in the Directory
thermal management system

Flight controls

Crouzet
pilot inceptor (control stick)

Structures

Aciturri / Sonaca España· not listed in the Directory
wing skins, spars, leading and trailing edges

Supplier list drawn from Eve, supplier and trade-press announcements as of 9 Nov 2026. Landing-gear, flight-control-computer and battery-cell suppliers have not been published. Eve says 21 to 22 suppliers take part in its design reviews, and about 10 to 11 critical design reviews remain for completion by the end of 2026. No full transition, conforming prototype or certification date has yet been achieved.

Showing 1–1 of 6

Competitors

Approximate, published figures
Compared itemSeatsSpeed / rangeLayoutFlight-test status (latest found)Certification target
Eve eVTOL (reference)4 passengers + pilotspeed not published / 100 km (60 miles)Lift and cruise: 8 lift rotors + rear pusherUncrewed prototype, 73 flights, partial transition to 45 kt; full transition planned end 2026ANAC end 2028; FAA validation end 2028
Joby S4 (USA)4 passengers + pilotup to 200 mph / up to 100 milesSix tilting propellersPiloted full transitions flown (Dubai 2025); 17 aircraft in productionFAA stages 1–3 of 5 complete; GCAA approvals pending
Archer Midnight (USA)4 passengers + pilotup to 150 mph / up to 100 miles6 tilting front + 6 fixed rear propellersPiloted VTOL and conventional flights; fully piloted transition not confirmed (as of 7 Nov 2026)GCAA Restricted Type Certificate track; FAA Phase 3 of 4 closed

Free every Friday

Aerospace Garage Weekly

Market Pulse, the nine regions and a course of the week — one email, free every Friday.

Your email address is used only to send you the free weekly edition and is never sold or shared. You can unsubscribe from any edition.