Bishoftu International Airport (BIA), Ethiopia

✓ Concept✓ DesignBuild · NowTestCertificationIn service

Ethiopian Airlines aircraft at Addis Ababa Bole International Airport, the hub the planned Bishoftu airport is to succeed
Country and region
Ethiopia · Sub-Saharan Africa
Lead organisations
Ethiopian Airlines Group; Dar (design); Zaha Hadid Architects (design)
Last milestone
Main contractor selection moved from August 2026 to early January 2027 at bidders' request (announced at Ethiopian Airlines' annual briefing, reported 1 Aug 2026); AIIB held talks on participation on 9 Sep 2026 (10 Jan 2026)
Next milestone
Contractor selection, early January 2027; earthworks complete, January 2027; lender approvals, by March 2027; Phase One opening, 2030 (2030)

Why it matters

Planned 110 million-passenger hub; anchors Africa's largest carrier and creates large demand for MRO, cargo and aviation services.

Bishoftu International Airport is Ethiopian Airlines Group's planned new hub, about 40–45 km southeast of Addis Ababa. It is meant to replace Addis Ababa Bole International, which the airline's CEO Mesfin Tasew says is overcrowded and cannot be expanded further. Prime Minister Abiy Ahmed has called it "the largest aviation infrastructure project in Africa's history".

Design approach: Phase One has two independently operated Code 4E parallel runways, a 660,000 sq m terminal and capacity for 60 million passengers a year. At full build-out it will have four runways, parking for 270 aircraft and up to 110 million passengers a year. Freight capacity is about 4 million tonnes, according to Further Africa. Dar (Dar Al-Handasah) leads the design team (airfield, masterplan, terminal and airport city), and Zaha Hadid Architects is design architect for the terminal. The terminal has a single central spine linking the piers so that up to 80% of passengers can transfer without leaving the building. It also has a 350-room airside hotel, natural ventilation and solar power, and targets LEED Gold. The site sits about 400 m lower than Bole, so longer runways and thicker air let aircraft carry more weight on long routes. Plans include a 38 km high-speed rail line, a 12-lane highway and an Airport City for about 80,000 people.

Key dates: in August 2025 the African Development Bank (AfDB) and Ethiopia signed a mandated lead arranger agreement. AfDB is to raise about US$8–8.7 billion and offered US$500 million of its own, subject to approval. Prime Minister Abiy laid the cornerstone on 10 January 2026. That started US$610 million of earthworks, due to take about a year. In early 2026 Ethiopian released lender materials and, by April 2026, completed prequalification for four EPC-F (engineering, procurement, construction plus financing) packages: 33 places in total, 15 held by Chinese or Chinese-led groups.

Cost and funding: US$12.5 billion for Phase One (first billed at US$10 billion). Ethiopian Airlines is to fund 20–30% and lenders the rest. No loan agreements had been signed by August 2026, though lender interest was about US$8.5 billion. Ethiopian Investment Holdings approved a special purpose company to run the project.

Showing 1–4 of 5

Milestone path

  1. Aug 2025

    AfDB named lead arranger

    Achieved

    The African Development Bank and Ethiopia signed a mandated lead arranger agreement. AfDB is to raise about US$8–8.7 billion and offered US$500m of its own, subject to approval.

    Why it matters: AfDB's lead role is the anchor for the rest of the lender group.

  2. 29 Nov 2025

    US$500m pledge from Chinese lender

    Achieved

    At the Africa Investment Forum in Rabat, Ethiopian Airlines CEO Mesfin Tasew announced a US$500m pledge from a China-based lender (not named).

    Why it matters: It showed Chinese lender interest early, though it is a pledge, not a signed loan.

  3. 10 Jan 2026

    Cornerstone laid, earthworks begin

    Achieved

    Prime Minister Abiy Ahmed laid the cornerstone, starting US$610m of earthworks due to take about a year.

    Why it matters: The site is now active, with early works ahead of the main construction packages.

  4. 24 Mar 2026

    Financing talks with Italy

    Latest

    Ethiopia's Ministry of Finance held talks with Italian financing institutions on Bishoftu.

    Why it matters: Italian banks could join the lender group alongside Italian contractor Webuild's bid.

Showing 1–1 of 3

Systems and suppliers

Client, owner and government

Ethiopian Airlines Group (Ethiopia)· not listed in the Directory
(state-owned). Client, sponsor, holder of the design contract and future operator; to fund 20–30%.
Ethiopian Investment Holdings (Ethiopia)
Approved a special purpose company to oversee the project.
Ministry of Finance (Ethiopia)
Leads financing talks with lenders; estimated resettlement cost above US$350m.

Design

Dar (Dar Al-Handasah)· not listed in the Directory
Lead consultant: airfield design, airport masterplan, terminal design and airport city planning.
Zaha Hadid Architects (UK)· not listed in the Directory
Design architect for the terminal: planning, architecture and interiors.

Finance

African Development Bank (AfDB)
(multilateral development bank). Mandated lead arranger; up to US$500m of its own subject to appraisal; also tendered lenders' insurance adviser and financial model auditor roles (Apr–May 2026).
Asian Infrastructure Investment Bank (AIIB)
(multilateral). Talks April and 9 Sep 2026; no commitment.
US International Development Finance Corporation (DFC) and Export-Import Bank of the United States (US)
Interested; no commitment.

Main contractors not yet selected (selection due January 2027) and no loans signed as of 9 Nov 2026. Shortlist from Ethiopian Airlines' published EPC-F list.

Showing 1–1 of 4

Competitors

Approximate, published figures
Compared itemEthiopian Airlines GroupKSIADC (PIF)Government of Rwanda; Qatar Airways 60% (2019 deal); Mota-Engil contractor
Runways2 (Phase One), 4 final6 parallelNot stated in sources opened
Passenger capacity60m (Phase One); 110m final120m by 2030; 185m by 20507–8m (Phase I); 14m (Phase II, by 2032)
CostUS$12.5bn (Phase One)Not officially publishedAbout US$2bn expected (2023), up from US$818m (2016)
Opening2030 (Phase One)20302028 (latest reported target)

Free every Friday

Aerospace Garage Weekly

Market Pulse, the nine regions and a course of the week — one email, free every Friday.

Your email address is used only to send you the free weekly edition and is never sold or shared. You can unsubscribe from any edition.